Timeline vs Gantt: a decision guide
简介 / Introduction
Both visualize “things moving forward over time”, but they answer different questions. A timeline answers when did something happen; a Gantt chart answers how long does each task take and what does it depend on. Picking the wrong one loses information: a timeline cannot show duration, and a Gantt chart forces readers to hunt for date points inside bars. This article implements the same release plan in PlantUML and Mermaid, then gives a selection rule.
Note: PlantUML also ships a
timelinekeyword, but the puml.online rendering backend does not enable that diagram type (it returns a syntax error). The PlantUML example below therefore uses Gantt, which it handles very well; the PlantUMLtimelinesyntax is listed in the comparison table.
PlantUML 版
1 | @startgantt |
The PlantUML Gantt model is task entity + duration + dependency: [Task] lasts N days defines the duration, starts at [X]'s end declares that the task starts the moment X finishes, and is colored in styles a task on its own line. Project starts pins the chart’s start date — without it PlantUML uses today as the baseline, so the axis silently drifts over time. Always write it explicitly in a document that will be re-read later.
Mermaid 版
1 | timeline |
A Mermaid timeline starts with the timeline keyword. Text after a colon : is the event description, and more deeply indented lines become sub-items of the previous event; section introduces a parallel group heading. It emphasizes the narrative of time point + what happened rather than the width of a task, which makes it a good fit for release history, version evolution and roadmap milestones.
对比 / Side-by-side
| Feature | PlantUML | Mermaid |
|---|---|---|
| Gantt keyword | @startgantt |
gantt |
| Timeline keyword | timeline (not enabled on this backend) |
timeline |
| Task duration | lasts 10 days |
10d / 2w / 3m |
| Task dependency | starts at [X]'s end |
after X |
| Grouping | no sections, distinguish by task name | section blocks |
| Status marking | manual is colored in |
built-in done / active / crit |
| Milestones | milestone |
milestone (or 0d duration) |
| Today marker | draw it yourself | built-in todayMarker |
Selection rule: durations, dependencies and progress tracking → Gantt chart (both engines support it, Mermaid is faster to write); only date points, telling a history or milestone story → timeline (Mermaid is smoother, PlantUML needs backend support confirmed).
小结 / Wrap-up
A Gantt chart answers “how much longer?”, a timeline answers “when?”. Mermaid has complete syntax for both and renders them in a consistent style, which makes it the fastest option for documentation. PlantUML’s Gantt gives finer control over dependencies and colors, which suits formal scheduling documents. The cost of choosing wrong is missing information — a timeline drops duration, and a Gantt chart hides point events inside bars.
- Title: Timeline vs Gantt: a decision guide
- Author: puml.online
- Created at : 2026-10-31 09:00:00
- Updated at : 2026-11-26 01:07:01
- Link: https://puml.online/blog/timeline-vs-gantt-decision-en/
- License: This work is licensed under CC BY-NC-SA 4.0.